Report Back to Projects
Ongoing Borehole

Maombi community Borehole

Kilifi · Malindi · Kakuyuni

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects for FY 2024/2031
Contractor
Consultant
Start Date
20 Sep 2024
Planned End
20 Oct 2024
Actual End
20 Oct 2024
Scope of Works
Drilling and capping
Impacts
Improve access to water
Key Challenges
No Challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
400
Households
2,000
Population