Ongoing
Pipeline
Satellite community water project
Mombasa · Changamwe · Kipevu
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects for FY 2024/2032
Contractor
—
Consultant
—
Start Date
07 Aug 2024
Planned End
10 Aug 2024
Actual End
10 Aug 2024
Scope of Works
Pipeline Extension and civil works
Impacts
Improved access to water
Key Challenges
Project complete awaiting connection by NAIVAWAS
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
600
Households
3,000
Population