Report Back to Projects
Ongoing Pipeline

Satellite community water project

Mombasa · Changamwe · Kipevu

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects for FY 2024/2032
Contractor
Consultant
Start Date
07 Aug 2024
Planned End
10 Aug 2024
Actual End
10 Aug 2024
Scope of Works
Pipeline Extension and civil works
Impacts
Improved access to water
Key Challenges
Project complete awaiting connection by NAIVAWAS
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
600
Households
3,000
Population