Report Back to Projects
Completed Tree Nursery Approved

Lower Tana Delta Conservancy

Tana River · Garsen · Kipini West

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
-
Planned End
-
Actual End
-
Contractor
Tana Water and Sanitation Company
Consultant
None
Location Type
Rural
Target Areas
Garsen
Scope of Works
Launching of the project; Tree Nursery development; Planting of 3 acre mangroves in Darga Galge degraded area and training by KFS; Installation of 3 water tanks at Odole primary, Ozi primary school and Kibokoni primary; Development of management plan; Trainings of herders, conservancy board and local leaders; Development of land use plans and resource mapping; Alternative clean energy (biogas/ energy saving jikos); Development of grazing by-laws/county grazing bills; Purchase and Transport of 6,000 tree seedlings and plant seedlings trees along the riparian area/river bank.
Impacts
Increased water catchment area
Key Challenges
COVID and floods led to contract extension. Conservancy had trouble procuring items. Extra Capacity building done.
Remarks
Project Completed
GPS Coordinates
2.521302 40.528441
Funding Sources
Danida
🌍 Foreign · Grant
KES 38.7M
Total KES 38.7M
Beneficiaries
533
Households
2,665
Population
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18