Ongoing Borehole Approved

Ustawi Biriko Water Resource, Supply and Sanitation Project

Isiolo · Isiolo North · Chari

Overall Progress
40.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Start Date
12 Jul 2022
Planned End
-
Actual End
-
Contractor
Ms pumptech solutions
Consultant
None
Location Type
Rural
Target Areas
Bulesa
Scope of Works
Drilling of 1 No. borehole and fencing, 26.4 KW solar pumping system installation, 13 Kms HDPE pipeline extension, 1 No. 50m3 Ground steel tank, 240 domestic water connection, 2 No. Water troughs, CLTS triggering in 45 villages, 2 No 4 door VIP latrine, WASH business center, soap making, Excavation of a 50,000 m3 Water Pan, 1,000 trees planting in schools, demonstration farming of hay and Crop production, 2 No shade net for horticulture,
Impacts
increased access to water and sanitation services in ASAL areas and resilience to climate change
Key Challenges
Non-response bidders led to repeat of procurement process 3 times. Delay in project implemetation.
Remarks
On-going project
GPS Coordinates
0.96167 38.53696
Funding Sources
Danida
🌍 Foreign · Grant
KES 61.7M
Gok
🇰🇪 Domestic · Grant
KES 6.5M
Total KES 68.2M
Beneficiaries
780
Households
3,900
Population
Technical Specs
Volume Abstracted 216.00 m³/day
Storage Reservoir 50.00 m³
Distribution Lines 13.00 km
Connections 240
Non-Sewered Sanitation Facilities 8