North Horr integrated project

Marsabit · North Horr · Noth Horr, Maikona

Overall Progress
80.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Start Date
12 Jul 2022
Planned End
-
Actual End
-
Contractor
Ms famo contractors
Consultant
None
Location Type
Rural
Target Areas
Konon Gos
Scope of Works
1 No. Water Kiosk, 100 m3 Elevated steel tank, 2 No. Water trough, Rehabilitation of 2No. Water Kiosk, CLTS in 32 Villages, 3 No. 3 door VIP latrines, 30,000m3 water pan
Impacts
increased access to water and sanitation services in ASAL areas and resilience to climate change
Key Challenges
Flooding of Chalbi desert.
Remarks
On-going project
GPS Coordinates
3.325385 37.056134
Funding Sources
Danida
🌍 Foreign · Grant
KES 22.5M
Gok
🇰🇪 Domestic · Grant
KES 10.8M
Total KES 33.3M
Beneficiaries
251
Households
1,255
Population
Technical Specs
Volume Abstracted 160.00 m³/day
Storage Reservoir 100.00 m³
Distribution Lines 2.10 km
Water Kiosks 1
Non-Sewered Sanitation Facilities 9
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18