Ongoing Borehole Approved

Baomo Water Project

Tana River · Garsen · Garsen North Ward, Ndera, Mwina

Overall Progress
40.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Start Date
12 Jul 2022
Planned End
-
Actual End
-
Contractor
Zaheer Enterprises Ltd
Consultant
None
Location Type
Rural
Target Areas
Baomo
Scope of Works
Construct 30,000m3 water pan, drill & develop 1 borehole, 30 KW solar system, 10kms HDPE pipeline, 24m3 EST, 6 VIP latrines, 1 water kiosk, 2 yard taps, planting 400 trees, pump house, fencing, CLTS in 30 villages & soft components
Impacts
increased access to water and sanitation services in ASAL areas and resilience to climate change
Key Challenges
Flooding of the project site and low contractors capacity.
Remarks
On-going project
GPS Coordinates
1.91284 40.1178
Funding Sources
Danida
🌍 Foreign · Grant
KES 31.7M
Gok
🇰🇪 Domestic · Grant
KES 3.4M
Total KES 35.2M
Beneficiaries
200
Households
1,000
Population
Technical Specs
Volume Abstracted 160.00 m³/day
Storage Reservoir 50.00 m³
Distribution Lines 3.20 km
Water Kiosks 1
Connections 2
Non-Sewered Sanitation Facilities 12
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18