Report Back to Projects
Ongoing Water Supply

Chemususu Last mile Connectivity-Eldama Ravine Lot 1

Mombasa · Kisauni · Mwakirunge

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Chemususu Water Supply and distribution project
Contractor
Aquawetts Enterprises Limited
Consultant
GIBB Africa
Start Date
30 Apr 2024
Planned End
30 Jul 2024
Actual End
31 Dec 2024
Scope of Works
Construction of 18m high-50m3 pressed steel tank Masonry tank and 32.4km pipeline extension
Impacts
Improve access to water
Key Challenges
No challanges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
4,000
Households
20,000
Population