Report Back to Projects
Completed Borehole Approved

Nanighi water and sanitation project

Tana River · Bura · Hirima

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
-
Planned End
12 Jan 2020
Actual End
-
Contractor
Tana Water and Sanitation Company
Consultant
None
Location Type
Rural
Target Areas
Bura
Scope of Works
Hydrogeological survey, design, EIA, borehole development, solar pumping system, 50m3 steel tank on a tower, 3No. Water kiosks, 5km pipeline, VIP latrines, capacity building & accompanying measures
Impacts
Serving additional 15,000 people with water access. Employment creation and improved service levels.
Remarks
Project completed and operational
GPS Coordinates
0°50'45.51"S 39°50'22.21"E
Funding Sources
Danida
🌍 Foreign · Grant
KES 18.2M
Total KES 18.2M
Beneficiaries
250
Households
750
Population
Technical Specs
Volume Abstracted 120.00 m³/day
Storage Reservoir 50.00 m³
Distribution Lines 5.00 km
Water Kiosks 3
Connections 3
Non-Sewered Sanitation Facilities 2
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…