Ongoing
Pipeline extension
Approved
Mauna Obet Water Supply Project
Siaya · Ugenya · North Ugenya
Overall Progress
95.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Civil Scope Engineering Ltd, Berkai Engineering and Agricultural Supplies Ltd, Steimich Enterprises Ltd and Earthview Management Capital Ltd
Consultant
None
Location Type
Urban
Target Areas
Obet Centre
Scope of Works
• 9 km Pipeline extension
• 500 no. 15mm volumetric meters
• 1no 108m3 steel elevated tanks
• 1 no. yards taps
• 1 no. kiosks
Impacts
The project will improve water access for 12,200 people through a 9 km pipeline extension, 500 volumetric meters (15mm) for efficient distribution, a 108m³ steel elevated tank for storage, and enhanced accessibility via a yard tap and a water kiosk.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
none
GPS Coordinates
0.1998241
34.1210502
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.1M
Kfw
🌍 Foreign
· Grant
KES 16.4M
Total
KES 19.5M
Beneficiaries
2,440
Households
12,200
Population
Technical Specs
Storage Reservoir
108.00 m³
Treated Water Mains
9.00 km
Distribution Lines
9.00 km
Water Kiosks
1
Connections
500