Completed
Pipeline extension
Approved
Chamunyu-Mwamlai Water Pipeline Rehabilitation & Extension Project
Mombasa · Jomvu · Miritini
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Adnur Limited
Consultant
None
Location Type
Urban
Target Areas
Chamunyu and Mwamlai
Scope of Works
• 5.5 km Pipeline extension,
• 900 no. Consumer meters
• 1no. Metering 100mm
• 1no. Metering 90mm
Impacts
The project will improve water access for 18,145 people through 900 consumer meters for efficient distribution.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
none
GPS Coordinates
-4.0102730
39.6032583
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 2.9M
Kfw
🌍 Foreign
· Grant
KES 15.4M
Total
KES 18.4M
Beneficiaries
3,629
Households
18,145
Population
Technical Specs
Storage Reservoir
5.00 m³
Treated Water Mains
5.00 km
Distribution Lines
5.50 km
Connections
900
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18