Completed
Pipeline extension
Approved
Malava Water Project
Kakamega · Malava · Chemuche
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Eazores Entrprises Ltd
Consultant
None
Location Type
Urban
Target Areas
Malava
Scope of Works
• 4.6 km pipeline extension
• 1no. 250 m3 Elevated steel tank
• Rehabilitation of 1 no. pump house
• Procurement and installation of 1 no. submersible pump
Impacts
The project will improve water access for 2,690 people through a 4.6 km pipeline extension, a 250m³ elevated steel tank for enhanced storage, rehabilitation of an existing pump house, and the procurement and installation of a submersible pump to improve water supply efficiency.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
0.4479467
34.8513369
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Kfw
🌍 Foreign
· Grant
KES 16.6M
Total
KES 19.8M
Beneficiaries
538
Households
2,690
Population
Technical Specs
Storage Reservoir
250.00 m³
Treated Water Mains
4.60 km
Distribution Lines
4.60 km