Completed
Pipeline extension
Approved
Mkwakwani Kona Water Project
Kwale · Msambweni · Ukunda
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Azaa construction
Consultant
None
Location Type
Urban
Target Areas
Ukunda
Scope of Works
• 6.4 km Pipeline extension
• 150no. 15mm Volumetric meters
Impacts
The project will improve water access for 3,600 people through a 6.4 km pipeline extension and 150 (15mm) volumetric meters, ensuring efficient distribution and reliable service delivery.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
-4.2834543
39.5662451
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.1M
Kfw
🌍 Foreign
· Grant
KES 16.3M
Total
KES 19.4M
Beneficiaries
720
Households
3,600
Population
Technical Specs
Treated Water Mains
6.40 km
Distribution Lines
6.40 km
Connections
150