Completed
Public Sanitation
Approved
Kimbimbi PSF
Kirinyaga · Mwea · Nyangati
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Vegrevile Investment Company
Consultant
None
Location Type
Urban
Target Areas
Kimbimbi
Scope of Works
Standard PSF and Septic tank
Impacts
The project will enhance public sanitation for 800 people daily through construction of a Standard PSF
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
-0.6205702
37.3657651
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 1.0M
Kfw
🌍 Foreign
· Grant
KES 5.2M
Total
KES 6.2M
Beneficiaries
160
Households
800
Population