Report Back to Projects
Ongoing Water Supply

Chemususu Last mile Connectivity-Eldama Ravine Lot 2

Mombasa · Kisauni · Mwakirunge

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Chemususu Water Supply and distribution project
Contractor
Vango Roads Engineering Limited
Consultant
GIBB Africa
Start Date
30 Apr 2024
Planned End
19 Sep 2024
Actual End
31 Dec 2024
Scope of Works
Construction of 100m3 Masonry Tank and | 38.2km pipeline extension
Impacts
Improve access to water
Key Challenges
No challanges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
6,400
Households
32,000
Population