Report Back to Projects
Completed Rock catchment Approved

Kyuso Rock water supply

Kitui · Mwingi North · Mwingi

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Start Date
-
Planned End
-
Actual End
08 Jul 2024
Contractor
M/S Linawar contractors
Consultant
None
Location Type
Rural
Target Areas
Mwingi town
Scope of Works
Catchment Rehabilitation and water kiosk,Treatment works,Twin Toilet,Electromechanical works ,Transmission lines ,Distribution line ,Accompanying measures
Impacts
Improved access to clean water for more households
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
The project is complete and operational
GPS Coordinates
-0.5537290725679079 38.21500528603792
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 10.0M
Eu
🌍 Foreign · Grant
KES 26.5M
Total KES 36.5M
Beneficiaries
2,260
Households
11,300
Population
Technical Specs
Volume Abstracted 100.00 m³/day
Treatment Capacity 100.00 m³/day
Storage Reservoir 150.00 m³
Distribution Lines 25.00 km
Water Kiosks 4
Connections 100
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18