Report Back to Projects
Ongoing Borehole

Kapkosim borehole- drilling and equipping

Baringo · Baringo North · Barwessa

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Projects For FY 2024/2025- Under Planning and Design
Contractor
Consultant
Start Date
31 Mar 2026
Planned End
30 Jun 2026
Actual End
08 Jul 2026
Scope of Works
Drilling, equipping and civil works
Impacts
Improved access to water
Key Challenges
Budgetary allocation
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
320
Households
1,600
Population