Report Back to Projects
Proposed Borehole Approved

Manyatta Lengima borehole

Marsabit · Laisamis · Lengima

Overall Progress
0.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Horn of Africa -Ground Water for resillience Programme (HOAGWR)
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
CAS
Location Type
Rural
Target Areas
Lengima
Scope of Works
3No Solar Photovoltaic Pumping (PVP) System for Laisamis, Manyatta Lengima and Olturot Boreholes. Supply and installation of 41.125 km of various HDPE Pipeline sizes ranging from OD 50mm to 150mm and pressure rating as detailed Construction of separate community water point for livestock and domestic as given in the specifications. Construction/supply and installation of various sizes of Water Tanks Ancillary Works - Construction of Administration buildings, Pump House Control room, guard house and sanitation facilities as detailed
Impacts
To serve the estimated population. Specific to be updated
Remarks
Project at the design stage
GPS Coordinates
1.746456 37.59417
Funding Sources
Wb
🌍 Foreign · Loan
KES 57.6M
Total KES 57.6M
Beneficiaries
0
Households
5,757
Population
Technical Specs
Storage Reservoir 150.00 m³
Distribution Lines 9.38 km
Water Kiosks 2
Connections 10
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18
County Overview