Proposed
Borehole
Approved
Nyata Borehole
Wajir · Wajir North · Korondile
Overall Progress
0.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Horn of Africa -Ground Water for resillience Programme (HOAGWR)
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
Aarvee Associates
Location Type
Rural
Scope of Works
Proposed scheme. To be updated after completion of designs
Impacts
To serve the estimated population. Specific to be updated
Remarks
Project at the design stage
Funding Sources
Wb
🌍 Foreign
· Loan
KES 58.5M
Total
KES 58.5M
Beneficiaries
0
Households
4,320
Population
Created 16 Aug 2026, 14:25