Report Back to Projects
Completed Borehole Approved

Drilling, Equipping and Last Mile Connectivity of Kamungei Borehole

Nandi · Mosop · Ndalat

Overall Progress
100.00%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water for Schools
Start Date
-
Planned End
-
Actual End
-
Contractor
Welldan Contractors Ltd
Consultant
None
Location Type
Rural
Target Areas
Kamungei Secondary and Primary School and Kamung'ei Village
Scope of Works
Drilling and test pumping of borehole, Borehole equipping and solar system, Elevated Steel Tank 24m3 on a 12m High steel Tower, 1 Water Kiosk, Fencing and Gate and Last Mile Connectivity 5Km
Impacts
Increased acess to water to Kamungei Secondary and Primary School and Kamung'ei Village
Remarks
Project complete and comissioned and is being managed by the school committee
GPS Coordinates
0.43372529, 34.96189608
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 10.1M
Total KES 10.1M
Beneficiaries
311
Households
1,553
Population
Technical Specs
Volume Abstracted 102.60 m³/day
Storage Reservoir 24.00 m³
Distribution Lines 5.00 km
Water Kiosks 1
Connections 4
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18