Ongoing
Borehole
Approved
Drilling, Equipping and Last Mile Connectivity of Bwanda (Kisumu) Borehole
Kisumu · Kisumu West · Central Kisumu
Overall Progress
50.00%
Project Overview
Implementing Agency
State Department for Water and Sanitation
Programme
Water for Schools
Start Date
-
Planned End
-
Actual End
-
Contractor
Leebarn Builders Limited
Consultant
None
Location Type
Rural
Target Areas
Bwanda Primary School and surrounding community
Scope of Works
Drilling and test pumping of borehole,
Borehole equipping and solar system, Elevated Steel Tank 24m3 on a 12m High steel Tower,
1 Water Kiosk,
Fencing and Gate and Last Mile Connectivity 5Km
Impacts
Not attained as project is incomplete
Remarks
Project is 50% complete and stalled due to bankruptcy on the Contractor
GPS Coordinates
,-0.134501, 34.78605
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 10.0M
Total
KES 10.0M
Beneficiaries
329
Households
1,644
Population
Technical Specs
Volume Abstracted
21.60 m³/day
Connections
2
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18