Completed Pipeline extension Approved

Wote Water Supply Project Phase II (Emali Town)

Makueni · Kibwezi West · Emali/Mulala

Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Wote Water Supply
Start Date
02 Nov 2021
Planned End
10 Jan 2021
Actual End
10 Jan 2021
Contractor
Invegus Limited
Consultant
-
Location Type
Urban
Target Areas
Emali Town
Scope of Works
• Drilling and Equipping of 1 No. Borehole. • Construction of 100 m3 Steel Elevated tank • Laying of 9.75 Km long pipeline • Supply and installation of solar modules at Muuoni River Sump, • Supply and Installation of dosing units, • Construction of 5 No. water kiosks,
Impacts
The Project serves the residents of Emali Town augumenting the Nolturesh Water Supply
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to a committee appointed by County Government of Makueni
GPS Coordinates
37.4698,-2.0781
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 67.0M
Total KES 67.0M
Beneficiaries
2,000
Households
10,000
Population
Technical Specs
Volume Abstracted 1,500.00 m³/day
Storage Reservoir 100.00 m³
Treated Water Mains 1.75 km
Distribution Lines 8.00 km
Water Kiosks 5
Connections 300