Completed
Pipeline extension
Approved
Manooni Alt; Nol-Turesh-Kikumini-Ithumba Water Supply Project
Makueni · Kibwezi West · Nguu/Masumba
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Wote Water Supply
Start Date
-
Planned End
08 Jan 2022
Actual End
08 Jan 2022
Contractor
Perma Structural Engineering
Consultant
-
Location Type
Rural
Target Areas
Manooni
Ithumba
Scope of Works
• Offtake from Existing Nol Turesh Pipeline
• Laying of 20 Km pipeline
• construction of 150m3 masonry tank,
• Rehabilitation of 2 No. Water Kiosks within makasa area
• Construction of 2 No. Water Kiosks
Impacts
The project serve an 10,000 resident of Ithumba/ Kikumini. (2,000 households)
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to the County Government of Makueni
GPS Coordinates
37.58566, -2.04681
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 75.0M
Total
KES 75.0M
Beneficiaries
1,050
Households
5,250
Population
Technical Specs
Volume Abstracted
800.00 m³/day
Storage Reservoir
150.00 m³
Treated Water Mains
5.00 km
Distribution Lines
15.00 km
Water Kiosks
4
Connections
100