Completed
Borehole
Approved
Oldonyio Sampu water project
Kajiado · Kajiado East · Poka Kenyawa
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Water for Schools
Start Date
11 Apr 2021
Planned End
02 Feb 2022
Actual End
05 Mar 2022
Contractor
Shakaduo Company Limited
Consultant
-
Location Type
Rural
Target Areas
Community
Schools
Scope of Works
• Drilling and Equipping of borehole
• Distribution line for community
• Water kiosk and cattle troughs
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to the community
GPS Coordinates
37.59549, -2.35259
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.0M
Total
KES 9.0M
Beneficiaries
246
Households
1,230
Population
Technical Specs
Volume Abstracted
180.00 m³/day
Treatment Capacity
180.00 m³/day
Storage Reservoir
20.00 m³
Treated Water Mains
1.00 km
Distribution Lines
2.00 km
Water Kiosks
2
Connections
1
Created 16 Aug 2026, 14:46
· Last updated 16 Aug 2026, 17:18