Completed
Borehole
Approved
Malilima borehole water project
Kajiado · Kajiado Central · Dalalekutuk
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Drilling and Equipping 40No. Boreholes
Start Date
-
Planned End
01 Nov 2022
Actual End
04 Nov 2022
Contractor
Maasai Store Limited
Consultant
-
Location Type
Rural
Target Areas
Community
Schools
Scope of Works
• Drilling and Equipping of borehole
• Distribution line for community
• Water kiosk and cattle troughs
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to the community
GPS Coordinates
36.85945, -1.87026
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.0M
Total
KES 9.0M
Beneficiaries
236
Households
1,180
Population
Technical Specs
Volume Abstracted
100.00 m³/day
Treatment Capacity
100.00 m³/day
Storage Reservoir
10.00 m³
Treated Water Mains
0.40 km
Distribution Lines
1.00 km
Water Kiosks
1
Connections
1