Completed
River Intake
Approved
Mavoko Drinking Water Supply Project
Machakos · Mavoko · Athi River West, Katani, Kinanie/Mathani, Makadara, Muthwani
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Mavoko Water Supply
Start Date
07 Jan 2020
Planned End
03 Jun 2022
Actual End
03 Jun 2022
Contractor
ASPAC Int.(Sprl), Brussels, Belgium
Consultant
-
Location Type
Urban
Target Areas
Mavoko
Syokumau
Athi-River
Scope of Works
• Independent line from Nairobi Water Company,
• Rehabilitation and de-silting of KMC and Portland dams
• New Mavoko water treatment works of 10,000m3/day and pumping units,
• Construction of new pipeline works of over 70km including rehabilitation of the reticulation system.
• Construction of 2No. 2,500M3 Water storage tanks and 1No. 5,000M3 tank.
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to Mavoko Water and Sanitation Company
GPS Coordinates
36.98451, -1.46223
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 336.7M
Belgium
🌍 Foreign
· Loan
KES 2,104.7M
Total
KES 2,441.4M
Beneficiaries
100,000
Households
500,000
Population
Technical Specs
Volume Abstracted
10,000.00 m³/day
Treatment Capacity
10,000.00 m³/day
Storage Reservoir
10,000.00 m³
Treated Water Mains
36.00 km
Distribution Lines
83.00 km
Water Kiosks
5
Connections
500
Created 16 Aug 2026, 14:46
· Last updated 16 Aug 2026, 17:18