Completed Pipeline extension Approved

Masinga Cluster (Kaewa – Kangonde Water Supply Project P2)

Machakos · Yatta · Matuu, Kithimani

Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Masinga Cluster
Start Date
07 Jan 2021
Planned End
-
Actual End
-
Contractor
Perma Structural Engineering
Consultant
-
Location Type
Rural Urban
Target Areas
Matuu Kitui Kanyonyo
Scope of Works
• Construction of 21km water supply pipeline, water kiosks, • Construction of 150m3 water tank • Construction of 50m3 water sump • Supply and installation of booster pumping unit.
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to Yatta Water and Sanitation Company
GPS Coordinates
37.56083, -1.172845
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 71.0M
Total KES 71.0M
Beneficiaries
1,900
Households
9,500
Population
Technical Specs
Volume Abstracted 1,500.00 m³/day
Treatment Capacity 9,000.00 m³/day
Storage Reservoir 200.00 m³
Treated Water Mains 6.00 km
Distribution Lines 15.00 km
Water Kiosks 4
Connections 250