Ongoing
Sewerage
Approved
Wote Town Sewerage Project
Makueni · Makueni · Wote, Muvau/Kikumini, and Mavindini
Overall Progress
1.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Wote Water Supply
Start Date
06 Jan 2025
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Urban
Target Areas
Kamunyolo and Unoa
Scope of Works
(i) Construction of Wote WWTP of Capacity 1,500m3/day comprising inlet works, anaerobic ponds, facultative ponds, maturation ponds, sludge drying bed constructed wetlands, site entrance gate, security fencing, office building, staff houses, laboratory and other site ancillaries;
(ii) Construction of Trunk and Lateral Sewers length 24,644.60 m;
(iii) Supply of sanitation equipment including Suction truck 10m3 and Truck (7.5 tonne) with hydraulic host;
(iv) Implementation of 300 Nr. Consumer connections.
Impacts
(i) Project expected to employ 1,000 persons during implementation and 30 personnell during operation
(ii) To serve 10,000 people (2000 household)
Key Challenges
Lack of funds to commences the construction works even though the detailed designs are ready
Remarks
Detailed Designs Complete
GPS Coordinates
37.621556,-1.779394
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
2,000
Households
10,000
Population
Technical Specs
Wastewater Production Capacity
975.00 m³/day
Wastewater Treatment Capacity
1,500.00 m³/day
Trunk Sewer Main
14.00 km
Reticulation Sewer
10.64 km
Manholes
492
Sewer Connections (Households)
352
Created 16 Aug 2026, 14:46
· Last updated 16 Aug 2026, 17:18