Completed Sewerage System and water supply services Approved

Olkalou Town Sewerage Project

Nyandarua · Ol Kalou · Olkalou

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
10 Jan 2022
Planned End
09 Jan 2023
Actual End
-
Contractor
Sinohydro Corporation Ltd
Consultant
SCET-TUNISIE, GATH CONSULTING ENGINEERS & LOSAI MANAGEMENT LTD JV
Location Type
Urban
Target Areas
Ol Kalou town & environs
Scope of Works
Sewerage Works • Construction of Wastewater treatment plant (3,300 m3/day ) • Laying of trunk sewers • laying of secondary and tertiary sewers, • Construction of 1 No. Public Sanitation block • 500 No. customer connection Water Supply Works • Construction of a conventional water treatment plant (2,000 m3/day). • Laying a distribution main • Rehabilitation works for the existing 18 km Malewa transmission main • Construction of Administration/ laboratory building
Impacts
Improve access to water and sanitation
Key Challenges
No challenges
Remarks
Completed and operational
GPS Coordinates
-0.272699,36.3775152
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 59.0M
Adb
🌍 Foreign · Loan
KES 589.9M
Total KES 648.9M
Beneficiaries
6,100
Households
30,500
Population
Technical Specs
Volume Abstracted 2,000.00 m³/day
Treatment Capacity 2,000.00 m³/day
Storage Reservoir 1,000.00 m³
Treated Water Mains 18.00 km
Distribution Lines 10.00 km
Connections 500
Wastewater Production Capacity 3,000.00 m³/day
Wastewater Treatment Capacity 3,300.00 m³/day
Trunk Sewer Main 10.20 km
Reticulation Sewer 25.50 km
Manholes 50
Non-Sewered Sanitation Facilities 20
Sewer Connections (Households) 500
Created 16 Aug 2026, 15:10 · Last updated 16 Aug 2026, 17:18