Completed
Sewerage System
Approved
Narok Town Sewerage Project
Narok · Narok North · Narok Town
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
-
Planned End
01 Dec 2021
Actual End
01 Dec 2021
Contractor
Sinohydro Corporation Ltd
Consultant
Mangat IB Patel
Location Type
Rural Urban
Target Areas
Narok town & environs
Scope of Works
Construction of RE’s Office; Secondary Sewers –length of 26.1km-; Trunk Sewers of 14.2 Km,,Main Trunk Sewers of 11Km,Sewage Treatment Works (3,000m3 Capacity)Last Mile Connectivity Works 81kms of pipe dia 50, 75, 110 and 160mm & 169Nr Concrete Valve chambers 2400 water connections and 500 sewer connections
Impacts
Improve access to water
Key Challenges
No challanges
Remarks
The project was commissioned on 15th April, 2023 by His Excellency The President.
GPS Coordinates
-1.157011, 35.870514
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 171.4M
Adb
🌍 Foreign
· Loan
KES 1,714.2M
Total
KES 1,885.6M
Beneficiaries
21,900
Households
109,500
Population
Technical Specs
Distribution Lines
81.00 km
Connections
2,400
Wastewater Production Capacity
3,500.00 m³/day
Wastewater Treatment Capacity
3,500.00 m³/day
Trunk Sewer Main
25.00 km
Reticulation Sewer
40.70 km
Manholes
169
Sewer Connections (Households)
500
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18