Ongoing
Water Supply
Approved
Chemususu Last mile Connectivity-Rongai Lot 1
Nakuru · Rongai · Soin
Overall Progress
80.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Chemususu Water Supply and distribution project
Start Date
-
Planned End
-
Actual End
-
Contractor
Build Venture Limited
Consultant
GIBB Africa
Location Type
Urban
Target Areas
Rongai constituency and environs
Scope of Works
Construction of 18m high 50m3 Elevated Tank Construction of 3No Water Kiosk
24.2km pipeline extension
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Awaiting handover to the Water company
GPS Coordinates
-0.173534, 35.860417
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 23.9M
Total
KES 23.9M
Beneficiaries
3,000
Households
15,000
Population
Technical Specs
Volume Abstracted
35,000.00 m³/day
Treatment Capacity
35,000.00 m³/day
Storage Reservoir
50.00 m³
Treated Water Mains
24.20 km
Water Kiosks
3