Completed
Borehole
Approved
Nakabaran Borehole
Turkana · Loima · Turkwell
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Start Date
07 Mar 2024
Planned End
10 Mar 2024
Actual End
-
Contractor
Kiburu Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
Kaapus sub location
Scope of Works
Drilling, Equipping and Civil Works
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Complete and handed over to the community
GPS Coordinates
35.351570, 3.172200
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.8M
Total
KES 8.8M
Beneficiaries
800
Households
4,000
Population
Technical Specs
Volume Abstracted
24.00 m³/day
Distribution Lines
1.80 km
Water Kiosks
1
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18