Completed
Borehole
Approved
Sobea Ntarakwa Community Water Project Phase II
Nakuru · Rongai · Solai
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Start Date
04 Nov 2024
Planned End
05 Jan 2024
Actual End
-
Contractor
Yellowstone Engineering Limited
Consultant
-
Location Type
Rural
Target Areas
Sobea Ntarakwa Community
Scope of Works
Rehabilitation of borehole
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Pending works to be addressed before issuing of retention.
GPS Coordinates
-0.249152, 35.939660
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.9M
Total
KES 3.9M
Beneficiaries
400
Households
2,600
Population
Technical Specs
Volume Abstracted
60.00 m³/day
Storage Reservoir
24.00 m³