Ongoing
Water Supply
Approved
Katabwa Water Project
Baringo · Mogotio · Mogotio
Overall Progress
5.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Start Date
06 Jul 2024
Planned End
06 Jan 2025
Actual End
-
Contractor
Amicity Holdings Limited
Consultant
-
Location Type
Rural
Target Areas
Katabwa and adjoining areas
Scope of Works
100m3 Masonry tank, Intake weir and pipeline extension
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Project Ongoing
GPS Coordinates
-0.025771, 35.952694
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 4.8M
Total
KES 4.8M
Beneficiaries
300
Households
2,700
Population
Technical Specs
Volume Abstracted
50.00 m³/day
Storage Reservoir
100.00 m³
Connections
2
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18