Completed
Borehole
Approved
Migaa Nursery School Water Project
Nakuru · Molo · Sachangwan
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Muluna Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
Migaa Nursery School and adjoining areas
Scope of Works
Drilling, Equipping and Civil Works
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Complete and operational
GPS Coordinates
-0.298277, 35.803452
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.6M
Total
KES 8.6M
Beneficiaries
400
Households
2,000
Population
Technical Specs
Volume Abstracted
26.66 m³/day
Created 16 Aug 2026, 15:10