Ongoing
Borehole
Approved
Bahati II BH Water Project
Nakuru · Nakuru North · Bahati
Overall Progress
85.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Start Date
05 Jul 2024
Planned End
01 Aug 2024
Actual End
-
Contractor
Hydroventures limited
Consultant
-
Location Type
Rural
Target Areas
Bahati II and adjoining areas
Scope of Works
Drilling Equipping and civil works
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Equipping and civil works ongoing
GPS Coordinates
-0.231909, 36.116531
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.4M
Total
KES 9.4M
Beneficiaries
700
Households
3,500
Population
Technical Specs
Volume Abstracted
88.00 m³/day
Storage Reservoir
20.00 m³
Distribution Lines
1.84 km
Water Kiosks
1
Manholes
6