Completed
Borehole
Approved
St Francis Primary School Mukinyai Borehole Water Supply Project
Nakuru · Molo · Elburgon
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Tai Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
St Francis Primary School Mukinyai and adjoining areas
Scope of Works
Drilling, equipping and civil works
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Complete and operational
GPS Coordinates
-0.210193, 35.800088
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.7M
Total
KES 8.7M
Beneficiaries
800
Households
4,000
Population
Technical Specs
Volume Abstracted
88.00 m³/day
Storage Reservoir
20.00 m³
Water Kiosks
1
Created 16 Aug 2026, 15:10