Report Back to Projects
Ongoing Water Pan Approved

Lelgut Water Pan

Baringo · Baringo Central · Sacho Ward

Overall Progress
90.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Rotalink Engineering Company Limited
Consultant
-
Location Type
Rural
Target Areas
Lelgut and adjoining areas
Scope of Works
Construction of 18,000m3 water pan
Impacts
Improve access to water
Key Challenges
Works are complete awaiting inspection
Remarks
Project is 100% Complete
GPS Coordinates
0.330225300659352, 35.75003215161928
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 4.7M
Total KES 4.7M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Storage Reservoir 18,000.00 m³