Report Back to Projects
Proposed Borehole Approved

Perkerra Model

Baringo · Baringo South · Marigat

Overall Progress
0.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects for FY 2024/2034
Start Date
11 Oct 2024
Planned End
11 Nov 2024
Actual End
-
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
To be determined
Scope of Works
Drilling and capping
Impacts
Improved access to water
Key Challenges
Drilling Ongoing
Remarks
Works ongoing
GPS Coordinates
0.06863032344866944, 35.7730323559164
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 2.8M
Total KES 2.8M
Beneficiaries
600
Households
3,000
Population
Created 16 Aug 2026, 15:10
County Overview
Loading…
Loading…

Fetching entity performance details…