Ongoing
Borehole
Approved
Kipkamur Community BH
Baringo · Mogotio · Emining
Overall Progress
85.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects for FY 2024/2038
Start Date
10 Sep 2024
Planned End
10 Oct 2024
Actual End
10 Oct 2024
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Kipkamur Community and its environs
Scope of Works
Drilling and capping
Impacts
Access to clean water by the community
Key Challenges
85% Drilling and Test pumping done. Signboard pending
Remarks
85% Complete
GPS Coordinates
0.2245205435516517, 35.982417650662015
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.4M
Total
KES 3.4M
Beneficiaries
380
Households
1,900
Population
Created 16 Aug 2026, 15:10