Report Back to Projects
Ongoing Borehole

Lorengipi Borehole

Mombasa · Kisauni · Shanzu

Overall Progress
90.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Contractor
Savanna Drillers Limited
Consultant
Start Date
03 Jul 2024
Planned End
03 Oct 2024
Actual End
Scope of Works
Drilling, Equipping and Civil Works with elevated tower
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
600
Households
3,000
Population