Ongoing
Borehole
Lorengipi Borehole
Mombasa · Kisauni · Shanzu
Overall Progress
90.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Contractor
Savanna Drillers Limited
Consultant
—
Start Date
03 Jul 2024
Planned End
03 Oct 2024
Actual End
—
Scope of Works
Drilling, Equipping and Civil Works with elevated tower
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
600
Households
3,000
Population