Report Back to Projects
Ongoing Water Supply Approved

Construction of Mukurweni Water project

Nyeri · Mukurweni · Mukurwe-ini central

Overall Progress
80.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
10 Aug 2024
Planned End
-
Actual End
-
Contractor
Safeline Limited
Consultant
-
Location Type
Rural
Target Areas
Mukurweini Town
Scope of Works
Rehabilitation of Ngamwa,Ithanji and Karundu schemes with HDPE pipes for an approximate of 37km Laying of DN 63-25mm HDPE– 12 km Ngamwa scheme. Laying of DN 50-25mm HDPE– 15.2 km Ithanji scheme. Laying of DN 63-25mm HDPE– 10.3 km Karundu scheme. Rehabilitation of Ngimaini Kiboya dam spillway and installation of solar powered system.
Impacts
Improve access to clean water and provision of direct employment to locals
Key Challenges
Delay in the GOK counter fund.
Remarks
Improvement access to clean water
GPS Coordinates
58781.000000000,91323.000000000
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 23.0M
Total KES 23.0M
Beneficiaries
1,240
Households
6,200
Population
Technical Specs
Volume Abstracted 8,400.00 m³/day
Distribution Lines 37.00 km