Proposed
Water Supply Project
Approved
Karatina water project
Nyeri · Mathira · Karatina Town
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
National Urban Water Supply and Sanitataion Program (NUWASSAP) Ph II
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Urban
Target Areas
Karatina and environs
Scope of Works
Construction of 90 days water storage dam
Construction of 30,000m3/d conventional water treatment plant
Laying of 4km long Raw Water Gravity Main
Laying of transmission gravity water mains of
42km
Construction of 5 No. Reinforced Concrete tanks of capacities
Impacts
Improve access to clean water and provision of direct employment to locals
Key Challenges
Awaiting Funds allocation
Remarks
Designs complete
GPS Coordinates
36.63336111 ,0.63336111
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
20,000
Households
100,000
Population
Technical Specs
Treatment Capacity
30,000.00 m³/day
Created 16 Aug 2026, 15:50