Report Back to Projects
Proposed Water Supply Project Approved

Kamangura Water Project

Nyeri · Kieni · Gakawa

Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Kamangura and environs
Scope of Works
Construction of 1,000m3/d conventional water treatment plant
Impacts
Improve access to clean water and provision of direct employment to locals
Key Challenges
Awaiting Funds allocation
Remarks
Designs complete
GPS Coordinates
0.0745, 37.0615
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
1,000
Households
5,000
Population
Technical Specs
Treatment Capacity 1,000.00 m³/day
Created 16 Aug 2026, 15:50
County Overview
Loading…
Loading…

Fetching entity performance details…