Completed
Dam
Approved
Thimangiri Earth Dam
Meru · Imenti North · Abothuguchi Central
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water Harvesting Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Waki Clearing & Forwarding Agents Ltd
Consultant
-
Location Type
Rural
Target Areas
Abothuguchi Central
Scope of Works
Construction of Earth Dam - 20,000 m3 Storage Capacity
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
GOK late disbursments
Remarks
Complete
GPS Coordinates
-0.002060000,37.594840000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.0M
Total
KES 8.0M
Beneficiaries
300
Households
1,500
Population
Technical Specs
Storage Reservoir
20,000.00 m³
Connections
300
Created 16 Aug 2026, 15:50