Completed
Dam
Approved
Nginyo Earth Dam
Meru · Igembe North · Amwathi
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water Harvesting Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Shaljo Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
Amwathi
Scope of Works
Construction of Earth dam of 25,000 m3 Storage Capacity
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
GOK late disbursments
Remarks
Complete
GPS Coordinates
5.701944440,37.161388890
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.9M
Total
KES 9.9M
Beneficiaries
360
Households
1,800
Population
Technical Specs
Storage Reservoir
25,000.00 m³
Connections
360