Ongoing
Borehole
Approved
Kisima Secondary School Borehole
Meru · Buuri · Kisima
Overall Progress
50.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water for Schools
Start Date
-
Planned End
-
Actual End
-
Contractor
FAIJA LIMITED
Consultant
-
Location Type
Rural
Target Areas
Kisima Secondary
Scope of Works
Drilling, development and test pumping
Impacts
Provision of safe water when complete
Key Challenges
GOK late disbursments
Remarks
Procurement process completed awaiting issuance of Engineer’s Notice to Commence
GPS Coordinates
13451.000000000,319107.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.5M
Total
KES 3.5M
Beneficiaries
1
Households
1,000
Population
Technical Specs
Storage Reservoir
24.00 m³
Created 16 Aug 2026, 15:50
· Last updated 16 Aug 2026, 17:18