Proposed
Borehole
Approved
Kiguma Borehole
Meru · Tigania East · Karama
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
TBD
Consultant
TBD
Location Type
Rural
Target Areas
Kiguma village
Scope of Works
▪ Drilling, development and test pumping
▪ Equipping and last mile connectivity
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
Awaiting Funds allocation
Remarks
At Design stage. Awaiting Appraisal and Hydrogeological Survey.
GPS Coordinates
TBD
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
80
Households
400
Population
Created 16 Aug 2026, 15:50