Ongoing
Sanitation Project
Approved
Construction of Biogas Production Unit at Ngaru Girls High School
- · - · -
Overall Progress
5.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Programme
Start Date
01 Oct 2024
Planned End
01 Oct 2025
Actual End
-
Contractor
Ranju Ltd
Consultant
-
Location Type
Rural
Target Areas
Ngaru Girls High School
Scope of Works
Construction of an Anaerobic Reactor
Construction of a horizontal flow constructed wetland
Construction of a treated effluent recovery pond
Impacts
Provision of reliable sanitation facilty.
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Facilitation of capacity building training for future projects .
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.8M
Total
KES 9.8M
Beneficiaries
1
Households
1,000
Population