Report Back to Projects
Ongoing Water Supply

Kalokol Water Project

Mombasa · Likoni · Mtongwe

Overall Progress
80.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Contractor
Rotalink Engineering Company Limited
Consultant
Start Date
03 Jul 2024
Planned End
03 Jan 2025
Actual End
Scope of Works
32KM pipeline extension
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
600
Households
3,000
Population