Completed
Borehole
Approved
Makutano Dispensary Borehole
Embu · Mbeere South · Makima
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Universal Health Coverage
Start Date
-
Planned End
07 Nov 2024
Actual End
07 Nov 2024
Contractor
Go Bright Limited
Consultant
-
Location Type
Rural
Target Areas
Makutano Dispensary
Scope of Works
Drilling, development, test pumping and equipping with solar system
Equipping with solar powered system and associated works
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Late disbursement of government funds.
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
9915819.000000000,308110.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 7.9M
Total
KES 7.9M
Beneficiaries
1
Households
500
Population
Technical Specs
Volume Abstracted
28.80 m³/day
Storage Reservoir
24.00 m³
Water Kiosks
1